Miecznik Programme Advances as ORP Huragan Keel-Laying Nears
Date of publication: 16.11.2026

Poland’s Ministry of National Defence has confirmed that the keel-laying ceremony for the future ORP Huragan will take place in late November, ahead of Navy Day. It will be the third and, so far, final frigate being built under the Miecznik programme. As with the two previous vessels, the ceremony will be held at PGZ Naval Shipyard in Gdynia.

Construction of the future ORP Huragan began in April this year. The plan is for the ship to enter service alongside the future ORP Wicher and ORP Burza between 2029 and 2031/2032. The three frigates will join the Combat Ship Squadron of the 3rd Ship Flotilla, based at the Gdynia Naval Port.

It is worth noting that, in addition to PGZ Naval Shipyard, two subcontractors, both based in Gdynia, are also involved in building the frigate’s blocks and sections. CRIST S.A. is already working on the future bow section, while Remontowa Nauta Shiprepair Yard is to supply the stern. This arrangement is expected to accelerate work on the vessel. All blocks and sections will be joined in the hull assembly hall at PGZ Naval Shipyard. Work is currently under way there on the future ORP Burza, which was moved into the hall shortly after the launch and christening of the first frigate in the Miecznik programme. Meanwhile, ORP Wicher is alongside the shipyard, where further outfitting work is being carried out.

Launched in 2021, the Miecznik programme is currently the Polish Navy’s largest modernisation project of its kind. It is being delivered by the PGZ-Miecznik Consortium, comprising Polska Grupa Zbrojeniowa S.A. and PGZ Naval Shipyard sp. z o.o. The project’s foreign strategic partners are Babcock, Thales UK and MBDA UK. Subcontractors include the aforementioned CRIST S.A. and Remontowa Nauta Shiprepair Yard S.A.

A new force for the Polish Navy

The Miecznik-class frigates will be 138.7 metres long, with a maximum displacement of up to 7,000 tonnes. They will have a top speed of 26 knots and a cruising speed of 12 knots, with a range of 8,000 nautical miles. Each ship will have a crew of up to 187. The propulsion system will comprise four diesel engines in a CODAD (Combined Diesel and Diesel) configuration. Some engines will operate at lower, more economical speeds, while additional engines will be brought online when speed or power requirements increase.

The ships will be equipped with an integrated mission system comprising an integrated bridge, communications system, platform management system and combat management system. Their full combat management capability, sensors and effectors will include systems for air defence, anti-missile warfare, surface-to-surface and surface-to-land engagement, as well as torpedoes for anti-submarine warfare. The planned air-defence fit includes Mk 41 vertical launching systems (VLS) and missiles from the CAMM family.

For engaging surface and land targets, the frigates will be equipped with RBS15 missile launchers. Their gun armament will include an OTO Melara Super Rapid Strales 76 mm medium-calibre gun, two 35 mm OSU-35K guns, remotely operated weapon stations fitted with heavy machine guns, and manually operated machine guns. Their torpedo armament will comprise two torpedo launchers. The ships will also have medium- and long-range multifunction radars, a fire-control radar, electro-optical surveillance systems, and both hull-mounted and towed sonars. They will be fitted with electronic warfare systems and weapons designed to enable them to counter a wide range of threats.

Huragan and its naval heritage

The name Huragan is particularly significant for the third frigate. No Polish naval vessel has previously borne the name, although it has a history of its own. It was originally intended for the next Grom-class destroyer, which was to be built alongside Orkan at the then Naval Port Workshops in Gdynia. Work began in August 1939 but was halted by the outbreak of the Second World War. Steel plates originally intended for the ship’s hull were instead used to build the armoured train Smok Kaszubski, deployed by the Polish Army during the September Campaign.

For a brief period, between 1940 and 1941, a French Bourrasque-class destroyer, Ouragan, served with a Polish crew. Built in 1924, the ship was interned in Portsmouth, UK, following France’s defeat during the German invasion. She was loaned to the Polish Navy and operated as OF Ouragan, although she is sometimes incorrectly referred to as ORP Huragan. She was subsequently transferred to the British and then served with the French naval forces until 1949.

What comes next?

Under the current shipbuilding schedule, Burza is expected to be launched next year. Huragan, meanwhile, is due to enter the water after 2028. In the meantime, Wicher will continue to undergo outfitting before beginning sea trials ahead of its handover to the customer. Navy personnel are also conducting intensive training for the future crews. The new frigates will replace two older Oliver Hazard Perry-class vessels, ORP Gen. T. Kościuszko and ORP Gen. K. Pułaski.

At present, the Miecznik programme предусматриes the construction of three frigates based on the Arrowhead 140 design. However, Polska Grupa Zbrojeniowa S.A. believes that ordering a fourth vessel would benefit both national defence and the shipbuilding industry. In addition to strengthening the capabilities of the Polish Navy, another frigate would help maintain continuity of work and employment at the shipyards, as well as preserve the expertise developed during the programme.

Image: PGZ Stocznia Wojenna

Most recent